Thursday, 11 August 2011
Headland Park site establishment
3 March 2011
Construction of Sydney's new spectacular
Headland Park at Barangaroo is about to start following the
appointment of Laing O'Rourke to undertake early works on the
site.
Work will be undertaken in accordance with the
Barangaroo Headland Park early works project approval issued in
November 2010 by the NSW Department of Planning.
As you are aware from our previous
notifications, sewer relocation and cliff stabilisation works
commenced at the northern end of Barangaroo and Hickson Road in
November 2010 and were completed in February 2011.
The Headland Park is progressing the next phase
of early works activities. The Barangaroo Delivery Authority
has awarded the early works contract to Laing O'Rourke, which has
extensive experience in complex civil infrastructure and building
projects, following an open tender process.
These works will commence in March and firstly
it will include the erection of a perimeter fence, establishment of
site offices and environmental controls. In addition the
light poles will be pulled down, some of the pavement will be
removed, construction of retaining walls in preparation for receipt
of fill and a redirection of Sydney Water's sewer main under
Hickson Road to an existing pumping station on the southern end of
the site.
The hours of work will be 7am to 6pm Monday to
Friday and 8am to 3pm on Saturdays. Noise levels are not
expected to exceed the allowable levels.